Project goals: To determine the feasibility of a utility scale wind farm being constructed in the fields back campus.

Progress:

- I have talked with Arlene DeBlanc about possible government grants

- I have analyzed data from RP&L's tall towers survey.

- I have analyzed data from the Indiana Tall Towers Wind Survey

- I have analyzed the data from the weather station on the roof of Dennis

- I have contacted numerous manufacturers for price quotes and other information on possible turbines

- I have investigated various funding sources

Turbine Possibilities

Feasibility requirements

- Long blades (100M diameter+)

- Tall tower (100M+ height)

Candidates

Nordex N100

Fuhrlaender FL-2500

RE Power 3.3 MW

Siemens SWT-101

Vestas V-112

Vestas V-100

GE-2.5xl