=== Progress: === | === Progress: === | ||
* I have talked with Arlene DeBlanc about possible government grants | |||
* I have analyzed data from RP&L's tall towers survey. | |||
* I have analyzed data from the Indiana Tall Towers Wind Survey | |||
* I have analyzed the data from the weather station on the roof of Dennis | |||
* I have contacted numerous manufacturers for price quotes and other information on possible turbines | |||
* I have investigated various funding sources | |||
=== Turbine Possibilities === | === Turbine Possibilities === | ||
==== Feasibility requirements ==== | ==== Feasibility requirements ==== | ||
* Long blades (100M diameter+) | |||
* Tall tower (100M+ height) | |||
==== Candidates ==== | ==== Candidates ==== | ||
| Line 35: | Line 35: | ||
[http://www.gepower.com/prod_serv/products/wind_turbines/en/2xmw/index.htm GE-2.5xl] | [http://www.gepower.com/prod_serv/products/wind_turbines/en/2xmw/index.htm GE-2.5xl] | ||
=== Grant research === | |||
====[http://www.rurdev.usda.gov/rbs/busp/b&i_gar.htm USDA Guaranteed Loans]==== | |||
* B&I guaranteed loans | |||
* Cover up to 10 Million $ (up to 40 in some cases) | |||
* Guarantee 60-70% of the loans against default | |||
====[http://www.rurdev.usda.gov/rbs/busp/rbog.htm Rural Business Opportunity Grant]==== | |||
* Up to 50,000$ for economic development | |||
* Deadline for this year has already passed | |||
====[http://www.eda.gov/InvestmenttsGrants/PublicWorks.xml EDA Public Works Grant] | |||
* Average award of 9 Million $ | |||
* Must show that project will help the local economy | |||
Revision as of 22:56, 23 September 2009
Project goals: To determine the feasibility of a utility scale wind farm being constructed in the fields back campus.
Progress:
- I have talked with Arlene DeBlanc about possible government grants
- I have analyzed data from RP&L's tall towers survey.
- I have analyzed data from the Indiana Tall Towers Wind Survey
- I have analyzed the data from the weather station on the roof of Dennis
- I have contacted numerous manufacturers for price quotes and other information on possible turbines
- I have investigated various funding sources
Turbine Possibilities
Feasibility requirements
- Long blades (100M diameter+)
- Tall tower (100M+ height)
Candidates
Grant research
- B&I guaranteed loans
- Cover up to 10 Million $ (up to 40 in some cases)
- Guarantee 60-70% of the loans against default
- Up to 50,000$ for economic development
- Deadline for this year has already passed
- Average award of 9 Million $
- Must show that project will help the local economy