New page: Project goals: To determine the feasibility of a utility scale wind farm being constructed in the fields back campus. |
No edit summary |
||
| Line 1: | Line 1: | ||
Project goals: To determine the feasibility of a utility scale wind farm being constructed in the fields back campus. | == Project goals: To determine the feasibility of a utility scale wind farm being constructed in the fields back campus. == | ||
=== Progress: === | |||
- I have talked with Arlene DeBlanc about possible government grants | |||
- I have analyzed data from RP&L's tall towers survey. | |||
- I have analyzed data from the Indiana Tall Towers Wind Survey | |||
- I have analyzed the data from the weather station on the roof of Dennis | |||
- I have contacted numerous manufacturers for price quotes and other information on possible turbines | |||
- I have investigated various funding sources | |||
Revision as of 22:02, 23 September 2009
Project goals: To determine the feasibility of a utility scale wind farm being constructed in the fields back campus.
Progress:
- I have talked with Arlene DeBlanc about possible government grants
- I have analyzed data from RP&L's tall towers survey.
- I have analyzed data from the Indiana Tall Towers Wind Survey
- I have analyzed the data from the weather station on the roof of Dennis
- I have contacted numerous manufacturers for price quotes and other information on possible turbines
- I have investigated various funding sources